2024
Secretary Determination and Record of Decision – January

Secretary Determination and Record of Decision

2023
Final Report/Final EIS – December

Final Report/Final EIS

Draft Report/Draft EIS – September

The public is given the opportunity to respond to the draft EIS.

Technical Evaluations/Analysis and Environmental Compliance – Summer

Technical Evaluations/Analysis and Environmental Compliance activities take place.

Public/Agency Outreach – June

Public/Agency Outreach begins.

2022
Final FS/EIS – June

Submittal of Final FS/EIS to Assistant Secretary of the Army

2018
Public Comment Period – June

Public Comment Period Begins.

Independent External Peer Review – February

Independent External Peer Review begins, and consultation with U.S. Fish and Wildlife Service, and State Historic Preservation begins.

2017
Agency Technical Review Process – January

USACE begins the Agency Technical Review Process for experts within the U.S. Army Corps of Engineers to review and provide comments on the Draft Report.

2016
USACE Review Process – January

The Feasibility and Environmental Impact Report begins the USACE review process.

2007

  • Congress passes WRDA Section 3104 that authorizes the Rankin Hinds Pearl River Flood & Drainage Control District to proceed under Section 211 of WRDA 1996 to complete a Feasibility and Environmental Impact Report to address flood risk along the Pearl River.

2013

  • Rankin Hinds Pearl River Flood & Drainage Control District begins Feasibility and Environmental Impact Report.

  • Scoping meeting held in Jackson, MS.

  • Scoping meeting held in Picayune, MS.

2016

  • Feasibility and Environmental Impact Report begins USACE review process.

2017

  • USACE begins the Agency Technical Review Process for experts within the U.S. Army Corps of Engineers to review and provide comments on the Draft Report.

2018

  • Independent External Peer Review begins, Consultation with U.S. Fish and Wildlife Service, State Historic Preservation begins.

  • Public Comment Period Begins.

    Submit a Comment


     

    Mail Comments To

    Rankin Hinds Pearl River Flood & Drainage Control District
    P.O. Box 320790, Flowood, MS 39232