2007

  • Congress passes WRDA Section 3104 that authorizes the Rankin Hinds Pearl River Flood & Drainage Control District to proceed under Section 211 of WRDA 1996 to complete a Feasibility and Environmental Impact Report to address flood risk along the Pearl River.

2013

  • Rankin Hinds Pearl River Flood & Drainage Control District begins Feasibility and Environmental Impact Report.

  • Scoping meeting held in Jackson, MS.

  • Scoping meeting held in Picayune, MS.

2016

  • Feasibility and Environmental Impact Report begins USACE review process.

2017

  • USACE begins the Agency Technical Review Process for experts within the U.S. Army Corps of Engineers to review and provide comments on the Draft Report.

2018

  • Independent External Peer Review begins, Consultation with U.S. Fish and Wildlife Service, State Historic Preservation begins.

  • Public Comment Period Begins.

Submit a Comment


 